SEQR Timetable:
December 2010
- Reach agreement re lead agency and project sponsor designations (complete)
- Prepare matrix of permits and approvals (complete)
- Prepare project description (complete)
- Prepare list of involved and interested agencies (complete)
Jan 2011
- Contract with TG Miller for engineering services (complete)
- Prepare scoping document for review (complete)
Feb. 2011
- Prepare EAF Part 1 for review (complete)
- Finalize scoping document and EAF Part 1 (complete)
- City transmits final scoping document and EAF Part 1 to NYSDEC to initiate SEQR (complete)
March, 2011
- NYSDEC circulates scoping document and EAF Part 1 to interested and involved agencies for review and comment, along with declaration of intent to serve as lead agency
- NYSDEC publishes notice of scoping meetings
- NYSDEC assumes lead agency status
- City/NYSDEC/EcoLogic hold scoping sessions (2)- target date 3/24/2011
- Begin DEIS preparation
April 2011
- Continue DEIS preparation
May 2011
- Target: 5/15 for DEIS submittal for completeness and adequacy review (45 days)
June 2011
- NYSDEC and other agencies review DEIS for adequacy and completeness – complete by 6/30
- Declaration of complete
July, 2011
- Public review and comment (30 days, min)
- Compile comments and prepare responses
August-Sept, 2011
- FEIS and Findings Statements
|
|
|
|
|
|
 |